Li Huizhong, Guo Fei, Fu Shaojun, Hao Wenzhong, Li Zhi, 2016. Adaptation and Correction of Dynamic Penetration Rod Length. Earth Science, 41(7): 1249-1258. doi: 10.3799/dqkx.2016.103
Citation: Li Huizhong, Guo Fei, Fu Shaojun, Hao Wenzhong, Li Zhi, 2016. Adaptation and Correction of Dynamic Penetration Rod Length. Earth Science, 41(7): 1249-1258. doi: 10.3799/dqkx.2016.103

Adaptation and Correction of Dynamic Penetration Rod Length

doi: 10.3799/dqkx.2016.103
  • Received Date: 2015-09-30
  • Publish Date: 2016-07-15
  • In the geotechnical investigation of hydropower projects in western China, exploratory sampling and engineering property research are challenging on account of the thick overburden on the riverbed. The dynamic penetration test(DPT) has become the preferred method of in-situ tests for the river overburden layers in western China due to its simple operation and applicability for different soil types. The current standard only provides a correction method for the rod length within 20 m. For the problems of adaptation and correction of heavy and extra-heavy dynamic penetration rod length, there is always much controversy but rare research for a long time. To address this issue, a study is conducted, involving the following procedures. Firstly, combined with the field test and numerical simulation, the stress value of each monitoring point is obtained by monitoring the rod of field DPT. Then, LS-DYNA software is used for inverse analysis and relevant parameters are determinined. Lastly, different rod lengths of DPT, such as 25 m, 40 m, 60 m, 80 m and 120 m, are simulated, and the adaptation and correction of rod length are obtained. The research method and results can be used for reference in similar problems and other geotechnical investigation practices in areas with deep river overburden layers.

     

  • loading
  • Bai, J.Z., 2005.The Theoretical Basis and Example Analysis of LS-DYNA3D Software.Science Press, Beijing (in Chinese).
    Jiang, H.J., Li, C.A., Zhang, Y.F., et al., 2014.Origin of Meander Shape-Superimposed Valleys in the Middle Jialing River:Responses to Regional Geological Environment.Earth Science, 39(11):1666-1674(in Chinese with English abstract). http://en.cnki.com.cn/Article_en/CJFDTotal-DQKX201411012.htm
    Li, H.Z., Guo, F., Pan, Y.Z., et al., 2015.Study on Extension and Polynomial Fitting of Correction Factors of Heavy Dynamic Penetration and Extra Heavy Dynamic Penetration.Yangtze River, 46(1):30-35 (in Chinese with English abstract).
    Li, H.Z., Hao, W.Z., Xiang, J.B., et al., 2008.The Study of Sampling and the In-Situ Test and Laboratory Test in the River Thick Overburden Layers at the Wudongde Dam Site Area.Journal of Engineering Geology, 16(Suppl.):202-207 (in Chinese with English abstract). http://www.gcdz.org/EN/abstract/abstract10299.shtml
    Lin, Z.Y., 2005.Geotechnical Testing and Monitoring Manual.China Architecture & Building Press, Beijing, 238-261 (in Chinese).
    Ministry of Construction of the People's Republic of China, 2008.Technical Code for Building Pile Foundations (JGJ94-2008).China Architecture & Building Press, Beijing, 21 (in Chinese).
    Ministry of Construction of the People's Republic of China, 2009.Code for Investigation of Geotechnical Engineering (GB50021-2001).China Architecture & Building Press, Beijing, 141-142 (in Chinese).
    Ministry of Railways of the People's Republic of China., 2005.Code for Design on Subsoil and Foundation of Railway Bridge and Culvert (TB10002.5-2005).China Railway Publishing House, Beijing, 21-31 (in Chinese).
    Shi, S.Q., Kang, J.G., Wang, M., et al., 2009.Engineering Application of ANSYSLS-DYNA Software in Explosion and Shock.China Architecture & Building Press, Beijing (in Chinese).
    Shi, X.S., Cheng, Z.L., Zuo, Y.Z., et al., 2011.Density Identification Method of Dam Foundation Deep Overburden.Rock and Soil Mechanics, 32(7):2073-2084 (in Chinese with English abstract). http://en.cnki.com.cn/Article_en/CJFDTOTAL-YTLX201107027.htm
    Xu, H., Wang, M.Y., Cheng, Z.L., et al., 2008.Analysis of Effect of Canyon Terrain on Stress and Displacement of Cutoff Wall in Dam Foundation with Deep Overburden.Rock and Soil Mechanics, 29(Suppl.1):64-68 (in Chinese with English abstract).
    Zuo, Y.Z., Cheng Z.L., Ding H.S., et al., 2014.Study of Modified Coefficient of Dynamic Penetration Rod Length.Rock and Soil Mechanics, 35(5):1284-1288 (in Chinese with English abstract).
    白金泽, 2005.LS-DYNA3D理论基础与实例分析.北京:科学出版社.
    江华军, 李长安, 张玉芬, 等, 2014.嘉陵江曲流型叠置河谷成因对区域地质环境的响应.地球科学, 39(11):1666-1674. http://www.cnki.com.cn/Article/CJFDTOTAL-DQKX201411011.htm
    李会中, 郭飞, 潘玉珍, 等, 2015.重型超重型动力触探锤击数修正系数外延研究.人民长江, 46(1):30-35. http://www.cnki.com.cn/Article/CJFDTOTAL-RIVE201501010.htm
    李会中, 郝文忠, 向家菠, 等, 2008.金沙江乌东德水电站坝址河床深厚覆盖层勘探取样与试验研究.工程地质学报, 16(增刊):202-207. http://cpfd.cnki.com.cn/Article/CPFDTOTAL-GCDZ200810001041.htm
    林宗元, 2005.岩土工程试验监测手册.北京:中国建筑工业出版社, 238-261.
    中华人民共和国建设部, 2008.建筑桩基技术规范(JGJ94-2008).北京:中国建筑工业出版社, 21.
    中华人民共和国建设部, 2009.岩土工程勘察规范(GB50021-2001).北京:中国建筑工业出版社, 141-142.
    中华人民共和国铁道部, 2005. 铁路桥涵地基和基础设计规范(TB10002. 5-2005). 北京: 中国铁道出版社, 21-31.
    石少卿, 康建功, 汪敏, 等, 2011.ANSYS/LS-DYNA在爆炸与冲击领域内的工程应用.北京:中国建筑工业出版社.
    石修松, 程展林, 左永振, 等, 2011.坝基深厚覆盖层密度辨识方法.岩土力学, 32(7):2073-2084. http://www.cnki.com.cn/Article/CJFDTOTAL-YTLX201107027.htm
    徐晗, 汪明元, 程展林, 等, 2008.深厚覆盖层300 M级超高土质心墙坝应力变形特征.岩土力学, 29(增刊1):64-68. http://cpfd.cnki.com.cn/Article/CPFDTOTAL-ZGSL200811001014.htm
    左永振, 程展林, 丁红顺, 等, 2014.动力触探杆长修正系数试验研究.岩土力学, 35(5):1284-1288. http://www.cnki.com.cn/Article/CJFDTOTAL-YTLX201405010.htm
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Figures(12)  / Tables(8)

    Article views (5096) PDF downloads(8) Cited by()
    Proportional views

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return